In the third section, the facade works have been completed
RIEL Real Estate Corporation reports that the construction of Companion RC is actively pursued. The builders have completed the facade works in the third section. The construction of the boiler house and rainwater drainage networks is underway. This was announced by the construction project manager Viktor Pysarenko.
At the same time, it is reported that in the second section, windows are being installed (90% ready), the facade is being finished (85% ready) and the internal and rainwater drainage is being arranged.
It is also reported that in the first section, the laying of the outer walls of the seventh floor and interior partitions of the fifth and sixth floors is being performed.