To the news list
Finishing works are underway in the house No. 3 of the second stage
October 18, 2023
RIEL Real Estate Corporation reports that the construction of Сompanion RC is in progress. The builders perform finishing works in the common facilities of the house No. 3 of the second stage.
In the houses No. 1 and 2, internal sewer risers have already been laid.
In general, installation of heating metres and balancing valves is underway, and preparations for laying a high-pressure gas pipeline to the boiler room continue.
On the territory, preparations are being made for laying a road between the houses and arranging entrance groups.
You can find out more about the construction progress and the conditions for selling apartments in Companion RC in our sales department. Contacts are available at the link.