To the news list

Finishing works are underway in the house No. 3 of the second stage

October 18, 2023

RIEL Real Estate Corporation reports that the construction of Сompanion RC is in progress. The builders perform finishing works in the common facilities of the house No. 3 of the second stage.

In the houses No. 1 and 2, internal sewer risers have already been laid.

In general, installation of heating metres and balancing valves is underway, and preparations for laying a high-pressure gas pipeline to the boiler room continue.

On the territory, preparations are being made for laying a road between the houses and arranging entrance groups.

You can find out more about the construction progress and the conditions for selling apartments in Companion RC in our sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(032) 294-96-64
Feedback
The exchange rate as of 11/21/2024 is 41.35 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Companion. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.