Boilers of the roof boiler house are connected to gas supply in the second phase
The construction of the second stage of Companion RC is nearing completion. Another important stage has been completed at the site: a valve manifold box with a metering unit has been installed at the roof boiler house and the boilers have been connected to the gas supply. This is one of the key steps to ensure the stable operation of the heating system and the comfort of future residents.
In the second building, we installed lamps in the common areas and on the staircases, which provides high-quality lighting and comfort in the interior spaces.
The third building is still being landscaped. The screed in the common areas and basement apartments has also been completed.

You can find out more about the progress of construction and the conditions for selling apartments in the Companion RC in our sales department. Contacts are available at the link.